Rail federal money review hits delay on HART’s timeline

Honolulu’s request for $1.55 billion in federal money for rail is about two months behind HART’s own schedule. 

But the rail authority and Federal Transit Administration say the project still is likely to get the funding pledge this year.

According to HART’s timeline when it submitted the full funding grant application this summer, the request should have been through FTA review by the end of July. It was then supposed to have Office of Management & Budget and White House review by the end of August, then onto Congress for its 2-month review.

The application has not yet cleared the first stage with the FTA.

"I think the red flag is that the FTA does not want to move on this until they see the results of the first lawsuit and the second lawsuit and the mayor election," said rail opponent and federal lawsuit plaintiff Cliff Slater.

HART said in a statement: “We have been working closely with the FTA on our Full Funding Grant Agreement submittal and all indications we have received thus far have been positive. Our submittal should be going to the federal Office of Management and Budget shortly, then on to Congress for the required notification."

FTA spokesman Brian Farber told KHON2: “The Federal Transit Administration expects to sign a full-funding grant agreement to construct the Honolulu High Capacity Transit Corridor Project by the end of this year, barring any unforeseen complications.”
Meanwhile, Honolulu Mayor Peter Carlisle is in Washington and will be meeting with FTA Administrator Peter Rogoff and other federal officials this week.

The mayor told KHON2 in a statement: “The city continues to work closely with the federal government and from all indications we remain in good standing regarding the project’s funding."

Sen. Dan Inouye’s office confirmed the FFGA application has not yet been routed to Congress. Spokesman Peter Boylan said, “The Senator remains confident in the federal support pledged for the project. He continues to support this important public transportation project that will offer a much needed alternative to driving in a city that suffers from the worse traffic congestion in the country in a state that spent more than $4 billion last year on imported fossil fuel.”